/ Updated / 9 min read
Engineering underwriting team - Global RE Underwriting

Key takeaways
- The 2026 regional conflict slowed GCC project awards, but the upcoming pipeline is still around USD 2 trillion.
- Accumulation across giga-projects, contractor groups and flood zones matters more than single-policy maximum loss.
- Testing and commissioning, extreme heat and flash floods are the perils most often underestimated.
Slower, but still huge
The conflict in the region knocked project awards back in the first half of 2026. Kamco Invest expects a sluggish year with a rebound from 2027, and some energy assets in the Gulf have been under force majeure. Even so, Kamco puts the upcoming GCC pipeline at around USD 2 trillion, with Saudi Arabia accounting for roughly half.
Most of the big schemes are being rephased, not cancelled. For insurers that means a long tail of engineering risk now, which turns into property risk as projects complete. AGBI made the same point about Saudi insurers late last year.
Thinking in projects, not policies
Single contracts can carry sums insured in the billions, run for years and involve dozens of contractors on the same site. At that size, the maximum loss on one policy only tells part of the story.
We look at how exposure builds up across a whole giga-project, across one contractor group, and across a single area that could be hit by the same flood or storm.
The perils people underestimate
Extreme heat affects curing, materials and how much work crews can safely do, and it stretches timelines. Flash floods are rare in the Gulf, but when they come they can fill excavations, basements and plant rooms in a matter of hours.
Testing and commissioning is still where energy, desalination and power projects lose the most money. We pay close attention to commissioning plans, how involved the equipment manufacturer is, and how any prototype technology is treated.
The contractor is the risk
Often the most useful thing we can learn is who is building it. Their record on similar projects, how they run a site, how they manage subcontractors and their claims history usually tell us more than the sum insured.
We ask for project schedules, values by phase, geotechnical reports, flood studies where they matter, and a clear view of how the cedant adds up exposure across projects in the same programme.
Where surety comes in
Construction all risks cover protects the works. Performance, advance payment and retention bonds protect the project owner if the contractor fails. As projects get bigger, owners want more bond capacity, and payment pressure in a slower year makes contractor strength matter even more.
Global RE writes both engineering and bonds/surety reinsurance, so we look at contractor risk from both sides. We cover the surety side in more detail in surety in 2026. For cedants active in the GCC, that usually means a more consistent answer across their construction and surety programmes.
Frequently asked questions
- How big is the GCC construction pipeline in 2026?
- Kamco Invest puts upcoming GCC projects at around USD 2 trillion, with Saudi Arabia accounting for roughly half. Awards slowed in the first half of 2026 and a rebound is expected from 2027.
- What are the main construction insurance risks in the Gulf?
- Accumulation across very large projects, testing and commissioning of energy, power and desalination plant, extreme heat, and rare but severe flash floods.
- How does surety differ from construction all risks cover?
- Construction all risks cover protects the physical works against damage. Performance, advance payment and retention bonds protect the project owner if the contractor fails to deliver.


